Remixpoint opens sixth Japanese grid battery site in Shimane
The Tokyo-listed firm filed a notice with the Tokyo Stock Exchange after its 8,146 kWh storage facility entered the regional balancing market.

Key takeaways
- 1Remixpoint launched market operations for its 1,988 kW storage facility in Shimane on 17 November 2026.
- 2The site is the company's sixth battery plant to enter Japan's grid balancing market.
- 3Monthly gross revenue from the new facility is projected at approximately 15 million yen.
- 4The firm targets a total network of 48 grid battery storage installations by March 2029.
Remixpoint began operations at its 1,988 kW grid-connected battery storage station in Oda City, Shimane Prefecture on 17 November 2026. This is the sixth energy facility from the group to enter Japan's electricity supply and demand balancing market. The company said in a filing with the Tokyo Stock Exchange that the NC Oda City Nima Town Energy Storage Station has a rated output of 1,988 kilowatts and a total capacity of 8,146 kilowatt-hours.
The facility uses battery systems from CATL and power conditioning units from TMEIC. Remixpoint first connected the site to the regional grid on 5 June 2026 before starting final market entry on 17 November. It is one of four storage projects the firm decided to acquire in June 2026 to expand its energy business. The group uses these sites to provide standby power that keeps the national grid frequency stable as more solar and wind power comes online.
Management expects the Shimane site to bring in about 15 million yen in gross monthly revenue. The company said this estimate is conservative and matches the performance of its site in Tottori because both are in the Chugoku regional grid area. Sites in other regions often generate closer to 20 million yen per month. This projected income was not part of the 7.045 billion yen revenue forecast for the energy storage division issued in June 2026.
The station trades on the Japan Electric Power Exchange and the national balancing market. These markets pay battery owners to help stabilise grid frequency as renewable energy use grows across the country. Remixpoint plans to enter the site into the Japanese capacity market in 2030. The firm intends to develop a total of 48 high-voltage grid storage projects by March 2029, with 25 of those sites being directly owned by the company.
The group currently owns 12 energy storage projects in various stages of development. There are 7 joint projects with Nippon Battery Co. Ltd., while the company owns 5 directly through its own acquisitions. Active sites are now running in Tamana City, Sendai City, Kama City, Shirakawa City, Tottori City, and Oda City. The Sendai site entered the market on 23 June 2026, followed by the Shirakawa site in July and the Tamana site in August.
Six more grid projects will start operations or enter the market by the end of 2027. A facility in Kainan City, Wakayama, joined the grid on 9 November 2026 and should start market trading in February 2027. Other sites in Gifu, Kagoshima, and Nagano are scheduled for grid connection through the middle of next year. The company said its simulation of revenue is based on current market prices and data from its power aggregators.
CEO Yoshihiko Takahashi leads the firm's strategy of combining energy infrastructure with digital asset holdings. Remixpoint holds bitcoin in its corporate treasury alongside its physical power assets. The company said it will update its financial guidance if these energy operations significantly change its total earnings. It plans to build out its storage portfolio to generate revenue through a mix of energy trading and asset management.